Yes it is official since 9/10/2010! We are now officially live after being blessed by the Fire Marhsall and Building Inspector
We can now legally operate our new datacenter and open our door to our customers. As of today, we have around 200 servers and equipments already live in our new datacenter.
Following are the detailed updates of what had happened ever since our last big blog update. We will put it in sections and bullet points for easy reading.
DATACENTER FLOOR CONSTRUCTION
- Tearing of walls and core drilling has been completed. We do not anticipate performing any heavy duty construction anytime soon.
- We will be putting cages in parts of our datacenter for security purposes
- We will be polishing the floors once we are completely out of the construction mode.
- IP Cameras has been installed in different areas of the datacenter.
ELECTRICALS
- The generator is installed, and tested. We were able to successfully perform a full electrical load transfer to our generator successfully without causing any downtime. The transfer time to the generator was 10 seconds.
- We plan to perform semi annual full load transfer to the generator as part of a regular datacenter maintenance practice.
- We plan to fire up the generator weekly in order to ensure the startups procedure are correct.
- We plan to install additional power ducts in our datacenter so that we can readily deliver electricals to the server cabinets.
MECHANICALS
- The installation of the main duct has been completed.
- The CRAC Unit has also been installed and is now fully operational.
- The exhaust fans with dynamic speed and automated control has been installed in order to relieve static pressure in our datacenter.
NETWORKS
- We have completed the deployment of redundant Border/Core/Distribution routing infrastructure in our datacenter. Customers can now request redundant pair of network drops and we can service any kind of redundant routing and switching needs.
- Standby Cold Router has also been prepared in the new datacenter
- We will be delivering additional 10GE connectivity inside our datacenter in the coming month. We hope to be able to provide Multiple 1Gbps Feeds and Full 10Gbps of bandwidth needs in within 1-2 months.
Here are some photos that have been recently taken. Hope you enjoy it! Let us know if you would like to tour our datacenter
You can reach us at http://www.coloinseattle.com/contact/

The Crac Unit is now online! We’re taking in lots of free cooling from the cool Seattle weather right now.

The two Exhaust Fan installation has also been completed. The automated static pressure control has been deployed and these fans will rotate automatically with dynamic speed to releave static pressure in the datacenter.

All cabinets has been bolted down and ready to be online.

Cabinets with 1/4 rack, 1/2 rack and 1/6 rack has also been installed in our datacenter.

UPS installation, testing, and monitoring has been completed.

Cabinets are secured to the roof by this 45 degree angle mounting bracket.

IP Cameras has been installed all over the facility. Smile! you are on camera