Today is a historic day! Our datacenter has officially soft opened today and our first customer is actually moving in today!
Here are some of the highlight in bullet points for easy reading
1. The fire marshall has approved the occupancy of our new datacenter. We still cannot officially fill up the entire space today due to the incomplete mechanical project. However the marshall has been kind enough to let us be operational with a few cabinets.
2. The building inspector has also officially approved occupancy of our new datacenter on 7/23/2010.
3. Our network was officially up and running yesterday 7/23/2010. Thanks to jim and his 3 hour sleep per day working round the clock in order to ensure fiber connectivities between our Westin Building Network infrastructure and our new datacenter network infrastructure.
4. The new crac units has been delivered! Unfortunately we had to ship one back to Emerson because it was damaged during the shipment. We are looking forward to complete our mechanical project by mid August.
5. Generator WILL Be installed by next week
6. We are currently running the datacenter using temporary cooling.
7. We will be moving some of our Wowrack Corporate Servers into our new datacenter as well next week!.
Stay tuned for more photos next week.