We have finally completed the VCT tile installation! (pic below). The first batch of APC black cabinets has been ordered and we are looking for them to come in sometime next week. The electrical switch gears have also arrived (pic below) and awaiting installation soon (fingers crossed) :)

We are very happy with the professionalism and great help from the Sabey construction team so far. Kudos to the great team!


Installation of the VCT tiles is now completed. The datacenter space construction project is now almost completed!


Conduit Holes has been drilled.


Large electrical switch gears and conduits have arrived! Can’t wait to get these installed!


Some more photo shots of the electrical switchgears.


Some more photo shots of the electrical switchgears.