Skip to content


Update 8/18/2010

First off, we have to apologize for the super late update to this blog. Yes we are still alive and kicking that the project is definitely moving towards the right direction. We have completed the building of our MMR with relay racks and our network is already up and running in the new datacenter. The next big project is the installation of the mechanical equipments including CRAC, vents, Exhaust fans and duct works. We are now waiting for the first phase of mechanical project and electrical to be completed so that we can officially open our door for business! :)   

Following are some photos that was taken on the 2nd week of August. We will post more pictures as a lot has changed since the last time these photos were taken :) Enjoy!


This is the front appearance of our little Meet Me Room (MMR) where all of our networking gear lives and where all cabling will be terminated inside the datacenter. As you can see we are running fully redundant Cisco routing and switching infrastructure with border, core, distribution and access layers.


This Supervisor 720-3BXL is ready to crank out some serious routing horsepower!


These two huge exhaust fans are the workhorse of the datacenter and will exhaust hot air out of our facility. Our datacenter is engineered to have 80 air exchanges in an hour which means a full air exchange from outside air sucked by our crac units; delivered to these gigantic 70,000 cfm fans!


Shows how big the blade of the fan is. Certainly don’t want to be stuck in there unless you are Criss Angel.


On the first phase of our datacenter buildout, cold air will still be delivered by dropping air directly from our main duct.


The handsome look of our brand new Liebert 45tons Air Handler Crac Unit.


The Crac unit has been lifted off the ground and properly installed with this super heavy duty riser.


The building window has been taken out and replaced by these vents that will be mechanically controlled to determine whether or not to deliver outside air into the facility.


10 ton Moving Cooler Unit is currently in production is being used to deliver cold air to our entire datacenter since we are already hosting live customers!


The first fully stacked cabinet with 40 servers in our new datacenter!


yep, lots of cabling work done on this cabinet :)

Posted in Uncategorized.


SOFT OPENING: July 24, 2010

Today is a historic day! Our datacenter has officially soft opened today and our first customer is actually moving in today!

Here are some of the highlight in bullet points for easy reading :)

1. The fire marshall has approved the occupancy of our new datacenter. We still cannot officially fill up the entire space today due to the incomplete mechanical project. However the marshall has been kind enough to let us be operational with a few cabinets.

2. The building inspector has also officially approved occupancy of our new datacenter on 7/23/2010.

3. Our network was officially up and running yesterday 7/23/2010. Thanks to jim and his 3 hour sleep per day working round the clock in order to ensure fiber connectivities between our Westin Building Network infrastructure and our new datacenter network infrastructure.

4. The new crac units has been delivered! Unfortunately we had to ship one back to Emerson because it was damaged during the shipment. We are looking forward to complete our mechanical project by mid August.

5. Generator WILL Be installed by next week :)

6. We are currently running the datacenter using temporary cooling.

7. We will be moving some of our Wowrack Corporate Servers into our new datacenter as well next week!.

Stay tuned for more photos next week.

Posted in Datacenter.


Update July 20, 2010

A Lot of stuffs and progress has happened again in the datacenter buildout! We’re certainly excited as we are getting inch closer to our soft opening dates which could be as soon as next week! :) Some of the progress that has happened since last update are:

1. Our Fire sprinkler system installation has been completed. The Vesda system is in place, the monitoring systems are in place and we are awaiting fire marshall inspection later this week to complete our occupancy permit.

2. We have put up some colo fences in parts of our datacenter

3. The dark fiber run going back to our HQ in Westin Building downtown seattle has been completed

4. The mechanical main duct installation has been completed! Boy was our mechanical contractor super fast and efficient in installing these :)

5. Our network gears are being setup now as we speak. We will be running fully meshed Cisco powered backbone network with border, core, distribution and access layer.

6. We also have words that our Liebert CRAC Units (HVAC) has arrived 3 weeks early and they are already in town. We are expecting delivery as soon as mid of this week!

7. Yes we are fully energized on the power front. The Transfer switch, main panel, UPS, PDUs and installed electrical outlets are all ready to power up those servers :)

Did I say that we are excited again? ;)

The Curvy Main power conduit installation has been completed with tons of copper inside them that has been fully energized!


The UPS has also been energized last Friday and already serving power to our PDUs.


All the main power panel installation has been completed. The final product on our phase 1 Installation looks currently looks like this.


Notice the small little white square thingy in the middle of the pic? That is an iPhone to give you an idea of the size of the casing for what would be our exhaust fans. We are putting in big-assed fans in here to suck out all the hot air!


First Ladder rack on top of our networking panels have been installed!


Yeah, we love Chatsworth Stuffs :)


This bad boy was one of the culprit for the delay of our electrical install. However, we hope that having this Kirk Key system installed provide redundant generators support will prove worth it one day.


Since our mechanical permit was issued last week, we have proceeded with the installation of the Main Duct that will tie our HVAC Units. We designed an oversized duct in order to be able to push those air around or datacenter floors.


First colocation fence has been installed. Thanks to the 4 crews that have been working hard over the weekend to get this installed.


First look at contiguous cabinets inside our datacenter. Any takers? ;)


Very nice servertech switched PDU that we will be using throughout the datacenter.


208A outlets have been installed to facilitate our networking equipments.


After long wait, the VESDA (Very Early Warning Smoke Detection Solution) system is finally fully installed.


Sprinker communication system is also up and running now.


The infamous VESDA orange tube that runs throughout our datacenter sampling air.


You sniff? This little hole does! What an amazing environmental monitoring technology!


This bundle of cable is one of the most important milestone in our datacenter buildout. This is our dark fiber connectivity back to the Westin Building that will allow fiber connectivity between our routing equipments. Customer will also be able to get a transport back to the Westin Building MMR, effectively making our datacenter to be a carrier neutral facility.


Yes the CAT generator has been here for 2 weeks now. We are expecting these to be turned up sometime late this week after we have passed the final fire marshall inspection.


What a beautiful day! This is also a view that shows our datacenter building is higher than the I-5 freeway in the background :)

Posted in Uncategorized.


Our Mechanical Permit has been approved !

Just in time!

Our electrical project is wrapping up soon and we are looking forward to proceed with the mechanical project as soon as possible.

We will also be talking to Seattle City Light Rep next week to discuss our datacenter power efficiencies plan :)

Posted in Datacenter.


July 2010 Progress

There are lots of updates again since the last time we’ve made the blogpost. The electrical project has been making a very good progress and we are still in the process of completing our conduit and power cable run into the facility. We have made a last minute change in our electrical design and have decided to put in an extra kirk key interlock system that would allow us to have N+N redundancies in our generator design. This has pushed the electrical project a few weeks back for the provisioning and delivery of the kirk key system. Other than that, there has been a very good progress in the electricals. Conduit runs has been put in place, we now have lights! :) , power cable are being run inside the conduits, fiber conduits have been completed, ATS, Circuit breaker panels, UPS installation are ongoing, fire supression system installation is almost completed, and we even managed to bolt down a few cabinets!

enjoy the photos! :)


Electrical Conduits have been installed all over the datacenter floors


PDU installation is ongoing. Conduit has been fed from this PDU to different parts of the datacenter


Can’t wait to juice these circuits up!


Circuit breakers on top of cabinet has been installed and awaiting cable to be fed


Views of conduit being distributed from our PDU


Another Views of conduit being distributed from our PDU


UPS wiring


Automatic Transfer Switch power monitor clip.


One of our main electrical panel


Maintenance By Pass Unit


Huge Copper Electrical Wires!


Networking Rack has been setup and bolted to the ground. We are expecting to setup our Meet Me Room (MMR) and our Cisco gears in here.


Fire Supressant System


New Sprinkler installed.


One of the Hot Aisle


We now have light, yay!


Some cabinets have been bolted down to the ground


:’( Someone vandalize our van parked outside of our datacenter :’(

Posted in Datacenter.


Lotsa Updates in June!

There have definitely been tons of updates since we’ve last posted on this blog :) Sorry for the late posts, but the good news is that we’re still on track in our datacenter project. As you all know from previous blogs, the construction part of the datacenter buildout project has been completed and we are now working on the electrical infrastructure buildouts, installing new fire suppressant system, and start working on the mechanical buildouts.

Please read the comments below the photos that was taken today in order to find out what has been going on :)


The First Batch of the APC Cabinet order have arrived. We are just currently staging them in the datacenter floor and we will be installing them once we are almost thru with the electrical buildouts.


The efficient powerware UPS has also arrived and has been assembled together with the battery cabinet. We can’t wait to juice this baby up on the later part of the electrical project.


Guess the most important part of the electrical buildout is this transfer switch. This will be the primary power entrance into our facility and electricians are actively working on installation of this ATS as we speak.


Conduits that will juice up the Automatic Transfer Switch :)


Conduit entrance to the Automatic Transfer Switch waiting for precious copper!


Some 600amps breakers fed from the Transfer Switch.


Yeah, its still damn busy in here! :)


The new dry-pipe fire supressant installation has been completed. All pipes run has been completed and sprinkler head has also been deployed all over the datacenter. We are waiting for the VESDA system to be installed next.


New sprinkler pipe installation


The main electrical switch gear has been fenced up for security. We have some extra space for future switch gear as well in the future.

 
Power conduits has been cored into the wall of the building.

Posted in Datacenter.


Photos May 13, 2010

We have finally completed the VCT tile installation! (pic below). The first batch of APC black cabinets has been ordered and we are looking for them to come in sometime next week. The electrical switch gears have also arrived (pic below) and awaiting installation soon (fingers crossed) :)

We are very happy with the professionalism and great help from the Sabey construction team so far. Kudos to the great team!


Installation of the VCT tiles is now completed. The datacenter space construction project is now almost completed!


Conduit Holes has been drilled.


Large electrical switch gears and conduits have arrived! Can’t wait to get these installed!


Some more photo shots of the electrical switchgears.


Some more photo shots of the electrical switchgears.

Posted in Datacenter.


Electrical Switch Gears Have Arrived

yes! this is even more exciting news :) Our electrical switch gears, ATS have arrived today.

We have also started to perform core drilling project in our datacenter facility that will run electrical and fiber conduits. We promise to post more pics soon this week! :)

Posted in Datacenter.


Update Last Week of April

We have seen a very good progress over the past couple weeks. The drywall is now 95% complete and has been painted white, construction is moving along without much trouble and insulation foam installation on top of our datacenter has also been completed. VCT installation has been confirmed for next week and upon the completion of that, we are very close to wrapping up the construction phase of our datacenter and will be ready to move into the next phase which is mechanical and electrical phase. We are currently still debating whether to fill our datacenter up with APC or Rittal cabinets, but we have all agreed that we will settle with a black cabinet :) We hope to order these cabinets in about a week or so.

I would like to point out the insulation on the ceiling of our datacenter. If you notice, it is colored white and is designed to reflect heat. Another reason for us to insulate our ceiling is to prevent the hot air from heating up our ceiling, hence affecting our top floor neighbor cooling. By having this insulation in place, we are really working towards saving energy for our neighbor :) Yes we’d like to be a good neighbor and prevent power from being unecessary utilized within our building. Another step closer to our green datacenter initiave!


Dry Wall has been completed, mudded and painted.


Another shot of our datacenter drywall. As you can see paint is barely drying as it was literraly applied an hour prior to this picture being taken.


The old sprinkler system will be replaced and this photo also shows that we have drywalled the rest of the building’s old infrastructure.


This is the beautifully done ceiling insulation with foam. This foam is put in place to prevent hot air from heating up our top floor neighbor.


Another shot of the ceiling insulation.


Our mechanical team has completed the measurement of HVAC and ducting placement.


Our 1200amps @480V distribution switch installation has been completed. This will be the backbone to our datacenter power.


Installation completed on 4/25/2010!


Monster electrical switch, brand spanking new :)

Posted in Datacenter.


Photos Mid April

We have made quite a progress by this time. We have finalized all of our partners and vendors, electrical gears including UPS, ATS, PDU have been ordered. Mechanical ducting has also been sized and proposed… More detailed updates as we finalize our final design soon! Meanwhile here are some of the photos of the recent progress ….


This was the document that halted our project for almost 2 weeks :) Glad to finally get it stamped by the city!


Our Datacenter Mechanical Design paperworks.


The view from our balcony. As you can see our building is way above the city street, way above Seattle lightrail track, and way above the buildings in the lower part of the city. If you notice to the left behind the trees, it is the Seattle sound transit bus parking facility. Yes, we are certain that flooding is not a concern :)


Walled-off T-junction for building water pipes


Completed skeleton awaiting drywalls.


Electrical Switch Gear is in place on top of the concrete pads. This should be juiced up by end of this month!

Posted in Datacenter.